Thanks for Attending the June Open Houses
Thursday, 24 July 2008

Over 100 people attended the first round of Green Line Open Houses held at three locations in Northeast Baltimore on June 8th, 9th and 10th.

Read more...
Project Schedule
Wednesday, 23 July 2008

The MTA is currently developing a range of alternatives that will be presented to the public in the fall. Upcoming Public Meetings Include:

Fall 2008: Initial Definition of Conceptual Alternatives

Spring 2009: Detailed Definition of Conceptual Alternatives

Banner Drop Shadow
Banner Drop Shadow
Banner Drop Shadow
Banner Drop Shadow
Project Schedule PDF Print E-mail
schedule_graphic_1.jpg

Phase

Questions to Answer

Scoping and Problem Definition
(We are here)

What problems are we trying to solve?

What areas are we trying to connect?

How can we get people involved?

schedule_graphic_2.jpg

Phase

Questions to Answer

Develop Alternatives

June – Fall 2008

Present to public:
Fall 2008

What areas need stations?

What path should the alternative take?

What possible conflicts and opportunities should we be aware of?

schedule_graphic_3.jpg

Phase

Questions to Answer

Analyze and Refine Alternatives

Fall 2008 – Spring 2009

Present to public:
Spring 2009

Where should the stations be located?

How will the alternative fit on the street?

What are some of the impacts and benefits that may result?

schedule_graphic_4.jpg

Phase

Questions to Answer

Select Locally Preferred Alternative

Spring 2009-Winter 2009

How much will the alternatives cost?

How many people will use the system?

How can we move the project forward?

 